top of page

U.S. Local Permitting Delays: A Hidden Risk in Manufacturing Expansion

  • OneLink Solution
  • May 30
  • 1 min read

For overseas companies aiming to set up manufacturing operations in the U.S., the challenge is no longer just about finding a location or funding equipment — it’s the maze of local permitting and regulatory layers.


From industrial fire code compliance to environmental impact assessments, each region has its own unique pace and process. Manufacturers often encounter friction when expectations from global HQs do not match the slow-paced and fragmented American local administration.


Additionally, unions, zoning boards, and local community objections can cause unexpected delays. Working with a local consultant or legal team early on helps companies preempt timeline risks.


For example, in California and Illinois, some companies report up to 7 months of delay due to lack of upfront zoning awareness. Permitting delays can affect lease negotiations, vendor coordination, and even talent onboarding plans.


Businesses are encouraged to integrate regulatory buffer time into their Gantt charts and investment pitch materials.

 
 
 

Comentários


Featured Posts
Recent Posts
Archive
Search By Tags
Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Social Icon

© 2017 by OneLink Solution

Address: 309 4th Ave, San Francisco, CA 94118

Email:   Gary@One-Link.us

bottom of page